Las Vegas Sun

April 24, 2024

Digging on first ‘people mover’ tunnel nearly done at Las Vegas Convention Center

The Boring Company Begins Tunneling for Convention Center

Christopher DeVargas

The Boring Company prepares to begin tunnel work for the Las Vegas Convention Center’s underground people mover project. The machine, which will bore an average of 100 feet a day, was receiving final adjustments before starting to dig on Friday Nov. 15, 2019.

The Boring Company Begins Tunneling for Convention Center

Sections of the concrete tunnel lining is set up for display at the entrance to the 40-feet deep hole. The Boring Company will begin tunnel work for the Las Vegas Convention Center's underground people-mover project today, Friday Nov. 15, 2019. Launch slideshow »

Boring on the first of two “people mover” tunnels being dug as part of the Las Vegas Convention Center’s expansion project is nearly complete.

Las Vegas Convention and Visitors Authority officials said digging on the first tunnel, which is nearly a mile long, will likely finish this week.

“As of (Monday), we’re approximately 4,200 feet into the 4,300-foot first tunnel,” Brian Yost, LVCVA’s chief operating officer, said Tuesday during the group’s monthly board meeting.

Once the first tunnel is finished, the machine being used by the Boring Company will be lifted out of the ground at the far west end of the convention center campus and trucked back to the original starting point outside South Hall.

The machine will then begin to dig a second parallel tunnel.

Digging for the $52.5 million underground people mover transit system started in November.

The people mover, which will take meetings attendees from one side of the convention center’s 200-acre campus to the other, is part of a $1.5 billion renovation and expansion project. The underground transport system is expected to be finished in time for the CES 2021 gadget show in January.

Steve Hill, the authority’s CEO, said the Boring Company is tunneling 85 to 100 feet a day.

“The Boring Company has picked up speed from the first month of operation, as well as smoothed out that operation,” Hill said. “They’ll use the same boring machine for the second tunnel, and that will probably be the last time that machine is used. They are working on a machine that is significantly faster than the one they have now.”

Hill said the most difficult part left for the tunneling project will likely be completion of the only station out of three that will be underground.

That’s because the underground station will need to be built during a period between two conventions that will be using the parking lot above it.

“That will be the most time-constrained part of the process,” Hill said.

Work is expected to begin on the station following the RECon real estate show — one of the best attended conferences in Las Vegas — in May.